●REFINERY SCHWEDT , Germany
·Revision and Repair works of Boiler Pressure Parts – 2017.
·Prefabrication and Installation of Pipelines – 2017.
·Project Verbundstillstand Step 2, Teilprojekte TP3 – 2018.
·Prefabrication & Installation of Piping, Material 1.4541, 16Mo3, P235GH – TC1, A 335Gr.P5.
●NIS Gazprom Neft Refinery Pancevo
·Capital Modernization and Reconustruction of Refinery – 2012.
Mont-r has participated at Piping Installation part of total 2 237t in Refinery Pancevo since 2012, which has a Raw Oil processing capacity of 4.8 million tons per year.
·DCU Plant Project WP1, Unit S-5900 & S-5950 – 2019.
Pipe Erection at Unit S-5900, S-5950 & S-5300 – Area A4 Piping SMLS B36.10M BE A106-B, A312-TP304L A333-6, Including Prefabrication & Installation of Pipe Supports and Stem Tracing.
·Major Overhaul of the Pancevo Oil Refinery in 2019.
LOT 1 – Major Overhaul of FCC S-2300, S-2500 & Alkylation S-2600.
●Project: TRANSMISSION GAS PIPELINE (Interconnector) in Serbia, 2019. – 2020.
starts from the Bulgarian border to the border with Hungary Customer Gastrans, main Contractor Infrastructure Development & Construcion (IDC) & Srbijagas.
Start Date: May 2019. End Date: February 2020.
The company Mont-r participated in Mechanical Works on the Prefabrication and Installation of the:
·Valve Block BVS15 and Measuring STATION GMS4 near Gospodjinci.
·GMS1-BVS1-POSM Receipt Dispatching Purification Point – Station at the Vrska Cuka.
·Receiving and Dispatching Purification – Compressor Station near Velika Plana PLR (CS).
Total number of 40 000 WDI, Welding Joints 1150,
Piping Class 6CX0C3U & 6CX0C3A
Diameters: 48″ (1219 x 22.23 mm) 256 WJ, 36″ (914.4 x 17.48 mm) 25 WJ, 254″ (609.6 x 25.4 mm) 117 WJ, 18″ (457.2 x 20.62 mm) 258 WJ, 16″ 12″ 8″ 4″ 3″ 2″-1/2″.